Division 02 · PjM

Project Management

Project Management (PjM) focuses on the management of architectural projects, including organizing principles, contract management, and consultant management. Candidates should demonstrate an understanding of quality control, project team configuration, and project scheduling.

Passed
04/25/22

Study recommendations

  • The exam is 3 hours long and contains 75 questions.
  • Most questions are multiple-choice (choose one of four answers), with some drag-and-place and calculation questions.
  • Two case studies typically ask about project schedules, scope, and services. Allocate at least one hour for the case studies.
  • The exam does not require you to memorize all AIA contracts or detailed definitions of accounting terms.
  • Remember that every question is worth one point, regardless of difficulty. Plan your time carefully and do not spend too much time on any single question.

Exam contents (you must know)

01

Resource Management

Selecting a Consultant

  • First, consider the past working relationship with the consultant.
  • Then consider the consultant’s staff availability and fee.

Assess Staffing Needs for a Project

  • Principal, Project Architect, Architect, Designer, and Drafter.
  • Structural, Mechanical, and Electrical consultants (basic services).
  • Civil, Landscape, and Telecommunications consultants (additional services).

02

Project Work Planning

Project Scheduling

  • Milestone chart: suitable for a small project; lists only milestone dates.
  • Gantt chart: suitable for all projects; makes the work sequence easy to understand.
  • Critical Path Method: more often used in construction; understand the critical path versus float.

Project Communication

  • Manage client expectations. Clearly communicate what is included in the basic scope and what is an additional service.
  • Document agendas, meeting minutes, emails, and memos.
  • Contractor–owner and contractor–consultant communications go through the architect.

03

Contracts

AIA B101 — Owner / Architect

  • Architect’s responsibilities, owner’s responsibilities, and contractor’s responsibilities.
  • Basic services: Schematic Design, Design Development, Contract Documents, Bidding and Negotiation, and Construction Administration under a typical Design–Bid–Build delivery method.
  • Additional services: Programming, Landscape, Civil, Telecommunications, and LEED, as listed in the contract.
  • For out-of-scope items, the architect should request an additional service from the owner, then adjust the project compensation and schedule.
  • Requests for additional services may result from design changes after owner approval, changes in building codes and regulations, expedited drawing production, or changes to the initial information provided by the owner.

AIA A101 and A201 — Owner / Contractor

  • The contractor is responsible for paying for utilities at the construction site.
  • For uncovered work and unknown conditions, understand who is responsible for payment.
  • All submittals and RFIs should be sent from the general contractor to the architect.
  • Understand when to issue a Supplemental Instruction, Change Order, or Construction Change Directive.
  • Dispute resolution: the architect is the Initial Decision Maker, followed by mediation, arbitration, or litigation.

AIA C401 — Architect / Consultant

  • The consultant is responsible for code compliance and the accuracy of its portion of the work, including its own errors and omissions.
  • The prime owner–architect agreement is attached to the contract as an exhibit. The consultant is expected to provide the same standard of care.
  • The architect should furnish information requested by the consultant and coordinate code requirements and specification formats.

04

Project Execution

Construction Budget

  • The architect provides a cost estimate at each design phase: Schematic Design, Design Development, and Contract Documents.
  • If the lowest bid exceeds the construction budget, the architect needs to revise the scope, program, area, or materials without additional compensation.

Changes in Scope

  • The architect requests additional compensation and time when the owner requests an additional service.
  • Avoid internal scope creep. Clearly inform the team of the project expectations and scope of work.

Project Delivery

  • Design–Bid–Build, Design–Build, Fast Track, Construction Manager, and Integrated Project Delivery.
  • Under Design–Build and Construction Manager delivery methods, the architect is usually not responsible for preparing the project cost estimate but still needs to review constructability with the contractor.

05

Project Quality Control

Codes and Regulations

  • Always follow the most stringent code.
  • During permitting, the building official determines code and material compliance.

Project Quality Control

  • Process: checklists, standard details, and corporate procedures.
  • Checking: peer review, cross-checking, and third-party review.
  • The architect checks other disciplines’ drawings for consistency, including structural clearances, diffuser locations, etc.