Division 06 · CE

Construction & Evaluation

Construction & Evaluation (CE) focuses on construction contract administration and post-occupancy evaluation of projects. Candidates should demonstrate an understanding of construction contract execution, construction support services—including construction observation and shop drawing or submittal review—payment request processing, and project closeout. Candidates must also understand the evaluation of integrated building systems and their performance.

Passed
01/07/22

Study recommendations

  • The exam is 3 hours long and contains 75 questions.
  • The exam is mostly multiple choice, with about 15% drag-and-place, hotspot, and calculation questions.
  • Knowledge of construction details is required, especially masonry wall, roof, and foundation details.
  • Specification divisions are not tested, and straightforward questions are rare on the exam.

Exam contents (you must know)

01

Preconstruction Activities

Design-Bid-Build (DBB)

  • The owner signs separate contracts with the architect and contractor.
  • Often required for public projects, this method is likely to obtain the lowest price because of its competitive nature.

Design-Build (DB)

  • The owner signs a single contract with one design-builder for both design and construction services.
  • This method can reduce the risk of schedule and cost overruns.

Construction Manager as Advisor (CMa)

  • A separate party hired by the owner.
  • The CMa controls costs, advises on constructability and the construction schedule, reviews RFIs and submittals, and handles communications first.

Construction Manager as Constructor (CMc)

  • The CMc advises the architect on constructability, scheduling, project complexity, etc.
  • Usually near the end of Design Development, the CMc provides a Guaranteed Maximum Price (GMP) and construction schedule for the owner's approval.

Integrated Project Delivery (IPD)

  • The owner, architect, contractor, and advisor act as a single entity.

Bidding Procedure

  • Prequalify bidders based on financial reports, personnel, experience, references, size, bonding capability, and quality of work.
  • The architect's role during bidding includes publishing bid documents, answering bidder questions, and assisting the owner in evaluating bids.
  • The contractor requests consideration of substitutions 10 days before the due date and clarification 7 days before the due date. The architect provides a response or addendum 4 days before the due date.

Bidding Documents

  • Invitation to bid, Instructions to Bidders (A701), supplementary instructions, bid forms, bid security, and bonds.

Bid Pricing Terms

  • Base bid: the contract amount for the base scope.
  • Alternates: additions or deletions of elements.
  • Unit price: cost for portions of the work based on individual quantities.
  • Allowances: estimated costs covering equipment or elements whose prices have not yet been determined.

02

Construction Observation

Purpose of Observation

  • Become generally familiar with the progress and quality of the work.
  • Guard the owner against defects and deficiencies.
  • Determine whether the work is progressing in accordance with the construction documents.

Number and Time of Visits

  • Determined by the architect or specified in the Owner-Architect Agreement.

Field Report

  • Include the name and project number, field report number, date, time, weather, current work, number of workers in the field, observation notes and photos, assessment of conformance, and estimated completion.

Uncovering and Correction of Work

  • Nonconforming work: the contractor pays, but the owner may choose to accept the nonconforming work.
  • If the architect requests uncovering and the work conforms to the construction documents, the owner pays.
  • If the architect requests uncovering and the work does not conform to the construction documents, the contractor pays.

03

Administrative Procedures & Protocols

Minor Changes in the Work

  • A minor change does not change the Contract Sum or Contract Time.

Change Order

  • Involves a change in the Contract Sum and/or Contract Time and must be signed by the owner, architect, and contractor.

Construction Change Directive

  • Signed by the owner and architect to direct the contractor to proceed with changes when the contractor does not agree with the adjustment to the Contract Sum and/or Contract Time.

Construction Submittals

  • Submittals are not part of the Contract Documents; turnaround time is determined by the submittal schedule.
  • Shop drawings, samples, product data, and cut sheets.

Application for Payment

  • The architect approves or rejects the requested amount based on the Schedule of Values.
  • Reasons to withhold money include defective work, third-party claims, the contractor's failure to pay subcontractors, damages, or work that cannot be completed on time.
  • Retainage is withheld until final completion to protect the owner, usually 10% of the Contract Sum.

Disputes and Claims

  • When there is a conflict between the owner and contractor, the architect should first try to clarify the contract scope and requirements impartially.
  • The architect is often the Initial Decision Maker (IDM).
  • Claim → IDM resolution → mediation → arbitration or litigation.

04

Project Closeout & Evaluation

Substantial Completion

  • The contractor prepares a punch list for the architect to review during the inspection.
  • If all essential elements are complete, the architect issues a Certificate of Substantial Completion.
  • The owner may occupy the building for its intended use, and warranties begin.

Post-Occupancy Evaluation

  • Conducted 3-6 months after occupancy as an additional service.
  • Data may be gathered from the owner, users, visitors, occupants, etc.

Follow-Up Visit

  • Conducted 6-12 months after occupancy and included in basic services.
  • A walk-through with the owner to provide an evaluation and hear feedback.