Construction & Evaluation

Construction & Evaluation (CE) focuses on construction contract administration and post-occupancy evaluation of projects. You should be able to demonstrate an understanding of and abilities in construction contract execution, construction support services (including construction observation and shop drawing or submittal review), payment request processing, and project closeout. In addition, candidates must also demonstrate an understanding and abilities in project evaluation of integrated building systems and their performance.

Passed 01/07/22

Study Recommendations

  • The exam is 3 hours, and 75 questions.

  • The exam is mostly multiple choices, and about 15% drag and place, hotspot, and calculation questions.

  • Knowledge of construction detail is required, especially masonry wall, roof and foundation details.

  • Specifications divisions are not tested, and straight forward questions are rare in exam.


Suggested Readings

PPI ARE 5 Review Manual link

Chapters 49-51

The Architect's Handbook of Professional Practice link

Chapter 9: Design Project Delivery, Chapter 10: Design Project Management

AIA Contract Documents link

A101, A201, A701, G701, G702

Exam Contents

SECTION 1: Preconstruction Activities

  • Design-Bid-Build (DBB)

      • Owner signs a separate contract with Architect and Contractor

      • Often required for public project, it is likely to get the lowest price due to its competitive nature

  • Design-Build (DB)

      • Own signs a single contract with one design builder for both design and construction services

      • Reduce risk of schedule and cost overruns

  • Construction Manager as Advisor (CMa)

      • A separate party hired by owner

      • CMa controls cost and advise on constructability and construction schedule, reviews RFI + submittal and handles communications first

  • Construction Manager as Constructor (CMc)

      • CMc will advise architect constructability, schedule, complexed project, etc.

      • Usually during end of DD, will provide a Guaranteed Maximum Price (GMP) and construction schedule to be approved by Owner

  • Integrated Project Delivery (IPD)

      • Owner, Architect, Contractor, Advisor acts as a single entity


  • Bidding Procedure

      • Prequalification of bidders based on: financial report, personnel, experience, reference, size, bonding capability, quality of work.

      • Architect's role during bidding include publish bid document, answer bidder questions, assist owner to evaluate bids, etc.

      • Contractor requests substitution to be considered (10) days before due date, clarification (7) days before due date. Architect provides response or addenda (4) days before due date.

  • Bidding Documents

    • Invitation to bid, instruction to bidders (A701), supplementary instruction, bid forms, bid security, bonds.


  • Base Bid: contract amount of the base scope

  • Alternates: addition or deletion of elements

  • Unit Price: cost for portions of work based on individual quantity

  • Allowances: estimated cost to cover a equipment or element which the price has not yet been determined

SECTION 2: Construction Observation

      • Purpose of Observation

          • 1. Become generally familiar with progress and quality of work

          • 2. Guard owner against defects and deficiency

          • 3. Determine whether work is progress with construction documents

      • Number and Time of Visit: determined by the architect or specified in the Owner-Architect agreement

      • Field Report: include name/project number, field report number, date/time/weather, current work, number of workers in the field, observation notes/photos, assessment of conformance, estimated completion

      • Uncovering and Correction of Work

          • Nonconformance - Contractor pays, but Owner can choose to accept nonconforming works

          • Requested by Architect, and conforms to CD - Owner pays

          • Requested by Architect, and NOT conforms to CD - Contractor pays


SECTION 3: Administrative Procedures & Protocols

  • Minor Changes in the Work

      • Minor change does not change contract sum and time

  • Change Order

      • Involves a change in contract sum and/or time. Need to be signed by Owner, Architect, Contractor

  • Construction Change Direction

      • Signed by Owner and Architect to direct Contractor to procced with changes, when Contractor is not in agreement with the contract sum and/or time.


  • Construction Submittals

    • Not part of the contract documents, turnaround time determined by submittal schedule

    • Shop Drawing/Sample/Product Data/Cut Sheet


  • Application for Payment

      • Architect approve or reject the requested amount based on Schedule of Values

      • Reason to withhold money: defective work, 3rd party claim, contractor's failure to pay subs, damages, work cannot be completed on time

      • Retainage is withheld until final completion to protect the owner, usually 10% of the contract sum


  • Dispute and Claims

      • Architect should try to clarify the contract scope and requirement impartially first when there is a conflict between Owner and Contractor

      • Architect is often the Initial Decision Maker (IDM)

      • Claim IDM Resolution Mediation Arbitration/Litigation


SECTION 4: Project Closeout & Evaluation

  • Substantial Completion

      • Contractor prepares a Punchlist for the Architect to review during inspection

      • If all the essential elements are complete, Architect issues a Certificate of Substantial Completion

      • Owner can occupy the building for its intended use and warranties start

  • Post Occupancy Evaluation

      • Conducted 3-6 month after occupation, as an additional service

      • Data might be gathered from owner, user, visitor, occupants, etc.

  • Follow Up Visit

      • 6-12 month after occupation, included in the basic service

      • A walk-through with Owner, provide evaluation and hear feedback