Project Management

Project Management (PjM) focuses on the management of architectural projects, including organizing principles, contract management, and consultant management. You should be able to demonstrate an understanding of and abilities in quality control, project team configuration, and project scheduling.

Passed 04/25/22

Study Recommendations

  • The exam is 3 hours, and 75 questions.

  • The majority are multiple choices (choose 1-4), with a some amount of drag and place and calculation questions.

  • There are two case studies typically asks project schedule, scope, and service. Allocate at least 1hour for case studies.

  • The exam does not ask you to remember all AIA contracts and detailed definitions of accounting terms.

  • Remember every question is one point regardless of difficulty. Plan your time well and don't spend too much time on each question.

Suggested Readings

PPI ARE 5 Review Manual link

Chapters 4-6

The Architect's Handbook of Professional Practice link

See AHPP relevant Sections link

AIA Contract Documents link

A101, A201, B101, C401

Exam Contents (you must know)

SECTION 1: RESOURCE MANAGEMENT

  • Selecting a Consultant

      • First consider the past working relationship with the consultant.

      • Then consider their staff availability and fee.

  • Assess Staff Need in a Project

      • Principal, Project Architect, Architect, Designer, Drafter

      • Structural, Mechanical, Electrical (basic service)

      • Civil, Landscape, Telecommunication (additional service)


SECTION 2: PROJECT WORK PLANNING

  • Project Scheduling

      • Milestone Chart: for small project, only list milestone dates.

      • Gantt Chart: suitable for all projects, easy to see the work sequence.

      • Critical Path Method: more often used in construction, understand critical path vs float.

  • Project Communication

      • Manage client expectation. Clearly communicate what is basic scope and what is additional scope.

      • Document agenda, meeting minutes, emails, and memos.

      • Contractor-Owner, Contractor-Consultant communicate through Architect.

SECTION 3: CONTRACTS

  • AIA B101 - Owner/Architect

      • Architect's responsibility, Owner's responsibility, Contractor's responsibility.

      • Basic Service: Schematic Design, Design Development, Contract Documents, Bidding and Negotiation, Construction Administration, typical Design-Bid-Build.

      • Additional Service: Programming, Landscape, Civil, Telecommunication, LEED (listed in the contract).

      • Out of scope items: Architect always request additional service from Owner, then adjust the project compensation and schedule.

      • Request additional service: change of design after Owner approval, change in building code and regulation, expedite drawing production, change in initial information provided by Owner.

  • AIA A101 A201 - Owner/Contractor

      • Contractor is responsible to pay for utility at construction site.

      • Uncover work, Unknown condition, know who pays.

      • All submittals and RFIs should be sent from General Contractor to Architect.

      • Understand when to issue Supplementary Instruction, Change Order, and Construction Change Directive.

      • Dispute Resolution: Architect is IDM, mediation, arbitration, litigation.

  • AIA C401 - Architect/Consultant

      • Consultant is responsible for code compliance and accuracy of its portion of work, and responsible for its own error and omission.

      • The prime Owner-Architect agreement is attached to the contract as an exhibition, consultant expect to provide the same standard of care.

      • Architect should furnish information requested by Consultant, coordinate code requirement and specification format.

SECTION 4: PROJECT EXECUTION

  • Construction Budget

      • Architect provide cost estimate at each design phase, SD, DD, CD.

      • If the lowest bid is over construction budget, Architect need to revise scope, program, area, material without additional compensation.

  • Changes in Scope

      • Architect request additional compensation and time when owner request additional service.

      • Avoid internal scope creep, inform team clearly the project expectation scope of work.

  • Project Delivery

      • Design Bid Build, Design Build, Fast Track, Construction Manager, Integrated Project Delivery.

      • Design Build and Construction Manager delivery type, architect usually not responsible to prepare project cost estimate, but still need to review constructability with Contractor.

SECTION 5: PROJECT QUALITY CONTROL

  • Code and Regulation

      • Always follow the most strict code.

      • At permitting, building official determines code/material compliance.

  • Project Quality Control

      • Process: checklist, standard detail, corporate procedures.

      • Checking: peer review, cross check, third party review.

      • Architect checks other disciplines drawings for consistency: structural clearance, diffuser location, etc.